3500T press Φ550 mold making invite tenders file
YANGZI
Release Time:
2017-08-10
Nantong Jiangdong Carbon Co., Ltd.’s pressing and baking workshop needs to order a Ф550 mold according to production needs. In line with the principles of fairness, justice, voluntariness and integrity, it conducts public bidding and selects the best suppliers. The relevant matters are hereby announced as follows: 1. Requirements for mold making: 1. Manufacture and process according to drawing requirements; 2. Mold material: QT600-3 3. Castings must not have sand holes, looseness, cracks and other casting defects, and processing surfaces are not allowed to have repair welding phenomenon. 4. The castings need to be normalized and the hardness is HBW230~260. 5. The mold processing size and precision reach the figure
According to the production needs, the press baking workshop of Nantong Jiangdong Carbon Co., Ltd. needs to order a Ф550 mold, and in line with the principles of fairness, justice, voluntariness and integrity, open bidding for it and selecting suppliers on the basis of merit. The relevant matters are hereby announced as follows:
First, mold production requirements:
1. Production and processing according to the requirements of drawings;
2. Mold material: QT600-3
3. The casting shall not have sand holes, looseness, cracks and other casting defects, and the processing surface shall not be allowed to have repair welding phenomenon.
4. The hardness of the casting needs to be normalized to HBW230~260
5. The size and accuracy of mold processing meet the requirements of the drawings
3. Procurement period
This mold manufacturing cycle: completed within 45 days after the contract is signed, delayed by one day delivery, deducted 300 yuan / day per day, deducted from the contract payment.
4. Qualification requirements for bidding units
The manufacturing unit participating in the bidding must have relevant production qualifications and provide qualification documents when bidding;
5. Quotation method
This mold adopts a one-time quotation, and the mold is settled at this price after reaching the production requirements and acceptance.
6. Payment Methods
After the contract is signed, the advance payment is 30%, and the mold manufacturing is delivered to the demander, and 50% is paid after the experience is qualified, and the performance bond (interest-free) is returned, and the remaining 90% is paid as a warranty money, and the warranty period (one year) is paid after the expiration of the warranty period;
7. Bidding matters
The bidders began to collect the tender documents at the Engineering Equipment Division on August 2017, 8, and the bidders submitted the bids at 11 a.m. on August 2017, 8.
The bidding unit shall pay the document and information fee of 100 yuan and (5000,<> yuan of the bid deposit) at the company's accounting and financial office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, and the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)
8. Evaluation and determination of bids
The evaluation and determination of bids shall be conducted by the bidding unit in conjunction with all relevant departments, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.
Contact: Wang Xingshan Tel: 85559291, 1321615786
Bidding unit: Nantong Jiangdong Carbon Co., Ltd
2017 Aug 8