Tender documents for the production and installation of the crane

YANGZI


Release Time:

2017-10-18

In the rotary kiln plant of the pressure training workshop of Nantong Yangzi Carbon Co., Ltd., due to production needs, a new 2.8-ton single-beam crane was added. Based on the principles of fairness, justice, voluntariness, and integrity, public bidding was conducted for it, and the supply was selected based on the best Commercial construction unit. The relevant matters are hereby announced as follows: 1. Project overview and content 1. The project is located in the rotary kiln workshop of the company's pressure cultivation workshop, and a 2.8-meter single-girder crane is newly installed, which is used for lifting raw materials. The height of the single girder of the driving body is about 1.5 meters. The height of the single girder of the driving body meets the requirements for safe use and does not collide with other buildings and equipment.

In the rotary kiln plant of the pressure training workshop of Nantong Yangtze Carbon Co., Ltd., due to production needs, a 2.8-ton single girder driving car was added, and in accordance with the principles of fairness, justice, voluntariness and integrity, it was publicly tendered and the supplier construction unit was selected on the basis of merit. The relevant matters are hereby announced as follows:

 

1. Project overview and content

1. The project is located in the rotary kiln workshop of the company's pressure training workshop, and a 2.8 handsome single girder driving car is newly installed, which is used for raw material lifting. The single girder of the driving body is heightened, about 1.5 meters high, and the height of the single girder meets the requirements of safe use, does not collide with other housing buildings and equipment, and leaves a message of sufficient safety distance. The vehicle is equipped with a maintenance platform, about 10.5 meters long and 0.6 meters wide, climbing ladders installed on both sides, the height of the guardrail is flush with the height of the single girder, equipped with a load limiter, the remote control has an electric bell control, the side of the bus bus is equipped with a protective plate, and the anti-collision limit of the large car is installed. The car is not equipped with a cab and is operated remotely from the ground. The bottom plane of the hook is flush with the track plane to meet the production requirements.

2. The track gauge is about 10.5 meters, the rail top elevation is about 7 meters, and the actual size of the track gauge and rail top elevation is subject to the actual measurement of each bidding unit;

3. The contractor makes the car, installs and debugs it on site until it is delivered for use

4. The contractor must ensure the construction quality during the construction process, and the contractor and the contractor shall jointly accept it after the completion of the project;

5. The contractor constructs with its own equipment, labor services and technology; All materials and accessories required for this project shall be provided by the contractor, and the materials of the tendering party shall not be used;

6. The contractor shall take appropriate safety measures to ensure the safe and smooth progress of the construction process, and the safety measures fee shall be included in the project payment.

II. Project Requirements:

1. The remote control device must be selected Taiwan Yuding high-quality qualified products, and the warranty period is 1 year; Number of remote controls: 2;

2. The electric hoist adopts high-quality qualified products of Jiangyin Kaicheng brand; Lifting height 9 meters;

3. The driving manufacturing unit must have special equipment production qualification;

4. The project quality reaches the national special equipment acceptance standards, and the driving must obtain the relevant qualifications of the use license issued by the national special equipment management department, and can be put into use normally.

3. Project Duration

Construction period of this project: 20 days for arrival of the vehicle, 5 days for installation and commissioning after arrival.

4. Qualification requirements for bidding units

The construction unit participating in the bidding must have independent legal personality and special equipment installation and construction qualification;

5. Project quotation

This project adopts a one-time quotation; This price will be settled after the completion of the project;

6. Payment for the project

20% of the payment after the contract is made, 30% after the acceptance of the vehicle to the factory, and settlement according to the relevant regulations of the company after the completion of the project;

7. Bidding matters

The bidders began to collect the tender documents at the Safety Equipment Division on 2017 October 10 and submitted their bids at 18 a.m. on 2017 October 10.

The bidding unit shall pay the document and information fee of 100 yuan and (5000,<> yuan of the bid deposit) at the company's accounting and financial office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, and the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)

8. Evaluation and determination of bids

The evaluation and determination of bids shall be conducted by the bidding unit in conjunction with all relevant departments, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.

Contact: Ge Jianjun Phone: 85559291, 15996585816

 

Bidding unit: Nantong Yangtze Carbon Co., Ltd