Tender documents for the production and installation of the crane
YANGZI
Release Time:
2017-05-11
In the crucible production line (former impregnation workshop) of Nantong Yangzi Carbon Co., Ltd., due to production needs, a new 2.8-ton single-beam crane was added. Based on the principles of fairness, justice, voluntariness, and integrity, public bidding was conducted for it, and the best ones were selected. Select the supplier construction unit. The relevant matters are hereby announced as follows: 1. Project overview and content 1. The project is located in the company's crucible production line (former impregnation workshop) workshop, and a 2.8-meter single-girder crane is newly installed, equipped with a load limiter, and protection is installed on the side of the busbar. plate. There is no driver's cab for this vehicle, and it is operated by remote control on the ground. The cart is equipped with a limit ruler, and the limit position can be adjusted.
In the crucible production line (former impregnation workshop) of Nantong Yangzi Carbon Co., Ltd., due to production needs, a 2.8-ton single girder driving car was added, and in accordance with the principles of fairness, justice, voluntariness and good faith, it was publicly tendered and the supplier construction unit was selected on the basis of merit. The relevant matters are hereby announced as follows:
1. Project overview and content
1. The project is located in the company's crucible production line (original impregnation workshop) workshop, a new 2.8 handsome single girder driving vehicle, equipped with a load limiter, and a protective plate is installed on the side of the driving busbar. The driving car is not equipped with a cab, for ground remote control operation, the large car is equipped with a limit ruler, and the limit position is adjusted to make the limit of the two driving large cars work normally.
2. The track gauge is about 19.5 meters, and the actual size of the gauge and rail top elevation shall be subject to the actual measurement of each bidding unit.
3. The contractor makes the car, installs and debugs on site, reports for inspection and delivers it.
4. The contractor must ensure the construction quality during the construction process, and with its own equipment, labor and technology construction, the contractor can provide electric welding machine, oxygen and acetylene.
5. All materials and accessories required for this project shall be provided by the contractor, and the materials of the contractor shall not be used.
6. Since this project is a high-altitude operation, the contractor must take appropriate safety measures to ensure the safety and smooth progress of the construction process, and the safety measures fee is included in the project payment.
II. Project Requirements:
1 remote control device must be selected Taiwan Yuding products, electric hoist for Jiangyin Kaicheng brand, lifting height of 9 meters, cart motor for soft start motor, warranty period of 1 year; The number of remote controls is 2.
2. The driving manufacturing unit must have special equipment production qualification.
3. The quality of the project reaches the national special equipment acceptance standard, and the driving must obtain the relevant qualification of the use license issued by the national special equipment management department, and can be put into use normally.
3. Project Duration
Construction period of this project: 20 days for the arrival of the vehicle, 5 days for installation and commissioning after arrival.
4. Qualification requirements for bidding units
The units participating in the bidding must have independent legal personality and special equipment installation and construction qualifications;
5. Project quotation
This project adopts a one-time quotation; This price will be settled after the completion of the project;
6. Payment for the project
20% of the payment after the contract is made, 30% after the acceptance of the vehicle to the factory, and settlement according to the relevant regulations of the company after the completion of the project;
7. Bidding matters
The bidders began to collect the tender documents at the Safety Equipment Division on May 2017, 5, and the bidders submitted the bids at 11 a.m. on May 2017, 5.
The bidding unit shall pay the document and information fee of 100 yuan and (5000,<> yuan of the bid deposit) at the company's accounting and financial office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, and the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)
8. Evaluation and determination of bids
The evaluation and determination of bids shall be conducted by the bidding unit in conjunction with all relevant departments, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.
Contact: Ge Jianjun Phone: 85559291, 15996585816
Bidding unit: Nantong Yangtze Carbon Co., Ltd
2017 May 5