Tender documents for roof waterproofing works

YANGZI


Release Time:

2017-06-07

The roof waterproofing project of Nantong Yangzi Carbon Co., Ltd., in line with the principles of fairness, impartiality, openness and voluntariness, conducts fair bidding to the outside world and selects the best construction unit. The relevant matters are hereby announced as follows: 1. Project overview 1. Making waterproof membranes The name and area of ​​the building (1): The roof of the ninth floor of Zhongsha broken, with an area of ​​about 300M2. (2): The stone-washed meeting room, with an area of ​​about 300M2 (3): Machining the A-line lounge, the second-level warehouse, with an area of ​​about 100M2 (4): Machined B-line fan room, with an area of ​​about 60M2 (5): High-end capacitor room, with an area of ​​about

Nantong Yangzi Carbon Co., Ltd. roof waterproofing project, in accordance with the principles of fairness, justice, openness and voluntariness, conduct fair bidding and select the construction unit on the basis of merit, and hereby announce the following related matters:

 

I. Project Overview

1. The name and area of the building where the waterproofing membrane is made

(1): The roof of the ninth floor is crushed, with an area of about 300M2.

(2): Immersion stone into a conference room, with an area of about 300M2

(3): Machining A-line lounge, secondary warehouse, area of about 100M2

(4): Machining B-line fan room, area of about 60M2

(5): High distribution capacitor chamber, area of about 50M2

(6): The duty room of the transfer station, with an area of about 40M2

(7): Machining electrical material library, area of about 40M2

(8): Attached room of machining C line, with an area of about 600M2

2. Practice:

(1): Shovel the waterproof membrane of the original empty drum on the roof, and clean and transport.

(2): Paste the new national regular manufacturer SBS waterproof membrane to ensure that there is no leakage for five years.

(3): Finish cleaning up the site.

3. The name and area of the building where the roof tiles are captured

(1): 2500T hydraulic pump room, area of about 60M2

(2): Machining morning light roof, area of about 800M2

4. Practice:

(1): Sort out the red tile roof, catch tiles, and clean up.

(2): Replace the damaged old tile.

(3): Finish cleaning up the site.

5. Clean the eaves gutter in the rotary kiln, add a color steel plate retaining wall under the eaves gutter, and the amount of work is self-measured.

2. Qualification requirements for bidding units

The construction unit participating in the bidding must have independent legal personality and relevant construction qualifications.

3. Project quotation

The membrane waterproofing of this project adopts a one-time unit price, and the actual area is settled after the completion of the project. The remaining projects are quoted as sub-prices and total prices, which are settled after the completion of the project

4. Project Period

The duration of this project is 30 days

5. Project quality

The quality of this project reaches excellent, and the warranty period is '5 years.

6. Payment for the project

After the completion and acceptance of the project, the construction unit needs to deduct 10% of the quality deposit and return it after one year, and the rest shall be settled according to the relevant regulations of the company.

7. Bidding matters

The bidders began to collect the tender documents at the Engineering Equipment Division on June 2017, 6, and the bidders submitted the bids at 7 a.m. on June 2017, 6.

The bidding unit shall pay the document and information fee of 100 yuan and (bid deposit of 10000,<> yuan) at the company's accounting office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)

VIII. Evaluation and Determination of Bids

The evaluation and determination of bids shall be conducted by the bidding unit in conjunction with the relevant departments, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.

9. Contact Information

Contact: Lin Qiang Tel: 051385559292, 051385559291

 

Bidding unit: Nantong Yangzi Carbon Co., Ltd

June 2017, 6