Environmental Improvement Project Five Bidding Documents
YANGZI
Release Time:
2017-08-01
The environmental improvement (ground part) project of Nantong Yangzi Carbon Co., Ltd., in line with the principles of fairness, justice, openness and voluntariness, conducts fair bidding to the outside world and selects the best construction unit. The relevant matters are hereby announced as follows: 1. Project overview: 1 , Machining the concrete floor in front of the D-line fan room. Requirements: A. The broken brick cushion layer is 150 thick. B. C30 concrete surface layer is 200 thick. C. On-site measurement of engineering quantities. D. The construction waste is transported outside the factory. 2. Slope at the north gate of the cold work shift in the motor workshop: Requirements: A. Remove the original slope surface and cushion. the
Nantong Yangtze Carbon Co., Ltd. environmental remediation (ground part) project, in line with the principles of fairness, justice, openness and voluntariness, conduct fair bidding and select the construction unit on the basis of merit, and hereby announce the following related matters:
I. Project Overview:
1. Pour concrete floor before machining D-line fan room.
Request:
A. The broken brick cushion is 150 thick.
B, C30 concrete surface layer 200 thick.
C. On-site measurement of engineering quantities.
D. Construction waste is shipped outside the factory.
2. Slope of the north gate of the cold work class of the motor workshop:
Request:
A. Eliminate the original slope surface layer and cushion layer.
B. Broken brick cushion 150 thick.
C, C30 concrete surface layer 200 thick.
D. On-site measurement of engineering quantities.
E. Construction waste is shipped out of the factory.
3. Guoyang crucible line middle channel:
Request:
A. Eliminate the original surface layer and cushion layer.
B. Broken brick cushion 150 thick.
C, C30 concrete surface layer 200 thick.
D. On-site measurement of engineering quantities.
E. Construction waste is shipped out of the factory.
4. Guoyang anode plate production workshop:
A. Replace the original color steel plate wall of the gable wall of the landlord of the factory.
B. The specifications and colors of the new color steel plate and C-shaped steel are the same as the original.
C. The dismantled waste materials are transported to the scrap iron yard.
5. The quantity of work shall be measured by each bidding unit on site according to the requirements of the contracting party, and if there are any incomplete matters, contact the contracting party before bidding.
6. The project is contracted for materials.
2. Qualification requirements for bidding units
The construction units participating in the bidding must have independent legal personality and civil engineering and above (including level 3) construction qualifications.
3. Project quotation
This project adopts a one-time quotation (each individual item is quoted separately), and this price is settled after the completion of the project. The quotation must contain the bill of quantities, the project budget, and the final quotation.
4. Project Period
Construction period: 20 days
5. Project quality
The quality of this project shall be qualified against the construction acceptance and other relevant acceptance standards. The warranty period is three years.
6. Payment for the project
After the completion and acceptance of the project, it will be settled according to the relevant regulations of the company.
7. Bidding matters
The bidders began to collect the tender documents at the Engineering Equipment Division on August 2017, 8, and the bidders submitted the bids at 2 a.m. on August 2017, 8.
The bidding unit shall pay the document and information fee of 100 yuan and (5000,<> yuan of the bid deposit) at the company's accounting and financial office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, and the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)
8. Evaluation and determination of bids
The evaluation and determination of bids shall be conducted by the relevant departments of the contract of the bidding unit, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.
9. Contact Information
Contact: Lin Qiang Tel: 051385559292, 051385559291
Bidding unit: Yangzi Carbon
August 0, <>