Environmental Improvement Project Six Bidding Documents
YANGZI
Release Time:
2017-08-01
The environmental improvement (roof part) project of Nantong Yangzi Carbon Co., Ltd., in line with the principles of fairness, justice, openness and voluntariness, conducts fair bidding to the outside world and selects the best construction unit. The relevant matters are hereby announced as follows: 1. Project overview: 1 , Packaging material warehouse roof. Requirements: A. Remove the original roof red tiles and wood base. . B. Using the original roof triangular purlins, install 160C steel or 50*50 square steel, and install 0.5MM thick sapphire blue color steel plate. C. The front and rear walls are repaired and the mountain is sealed. D. On-site measurement of engineering quantities. E. The construction waste is transported outside the factory. the
Nantong Yangtze Carbon Co., Ltd. environmental remediation (roofing part) project, in accordance with the principles of fairness, justice, openness and voluntariness, conduct fair bidding and select the construction unit on the basis of merit, and hereby announce the following related matters:
I. Project Overview:
1. Packaging material library roof.
Request:
A. Demolition of the original roof red tile and wooden base layer.
B. USE THE ORIGINAL ROOF TRIANGLE PURLIN, INSTALL 160C SECTION STEEL OR 50*50 SQUARE STEEL, AND INSTALL 0.5MM THICK ROYAL BLUE COLOR STEEL PLATE.
C. The front and rear walls are repaired and the mountain is closed.
D. On-site measurement of engineering quantities.
E. Construction waste is shipped out of the factory.
5. The quantity of work shall be measured by each bidding unit on site according to the requirements of the contracting party, and if there are any incomplete matters, contact the contracting party before bidding.
6. The project is contracted for materials.
2. Qualification requirements for bidding units
The construction units participating in the bidding must have independent legal personality and civil engineering and above (including level 3) construction qualifications.
3. Project quotation
This project adopts a one-time quotation (each individual item is quoted separately), and this price is settled after the completion of the project. The quotation must contain the bill of quantities, the project budget, and the final quotation.
4. Project Period
Construction period: 20 days
5. Project quality
The quality of this project shall be qualified against the construction acceptance and other relevant acceptance standards. The warranty period is three years.
6. Payment for the project
After the completion and acceptance of the project, it will be settled according to the relevant regulations of the company.
7. Bidding matters
The bidders began to collect the tender documents at the Engineering Equipment Division on August 2017, 8, and the bidders submitted the bids at 2 a.m. on August 2017, 8.
The bidding unit shall pay the document and information fee of 100 yuan and (5000,<> yuan of the bid deposit) at the company's accounting and financial office before receiving (submitting) the tender document, the document and information fee will not be refunded after the opening of the bid, and the bidding deposit will be refunded without interest if the winning unit does not win the bid after the bid is opened, and the winning unit will be converted into a performance bond. (Collect and submit the tender documents with the receipt of the Financial Planning Office)
8. Evaluation and determination of bids
The evaluation and determination of bids shall be conducted by the relevant departments of the contract of the bidding unit, and the bidding unit shall not be obliged to explain to the unsuccessful unit the reasons for not winning the bid.
9. Contact Information
Contact: Tel: 051385559292,051385559291
Bidding unit: Yangzi Carbon
August 0, <>